Timeline
May 2003

Rocket Team Starts
(Project Manager: Joey Brown)

Summer 2003Fabrication of Machezuma
Sept 20, 2003Machezuma Launch Attempt (hard start)
Fall 2003Fabrication of Phoenix
Dec 7, 2003Phoenix Launch called off at last minute due to weather conditions and Edwards AFB
March 6, 2004Phoenix Launch Attempt (max alt. 100 ft)
Spring-Summer 2004Fabrication of Phoenix II
Summer 2004Static Fire Test
Oct 23, 2004Phoenix II Launch Attempt (hard start)
Spring 2005Fabrication of Delta Phoenix
May 21, 2005Delta Phoenix Launch